NRA approves in principle proposal to let N-plants run over 60 years
17:50 JST, November 16, 2022
The Nuclear Regulation Authority on Wednesday approved in principle a plan that would allow the economy ministry to extend the operational life of nuclear power plants at intervals of within 10 years, beginning 30 years after the start of their use.
If this system is introduced, the current rules for nuclear power plants — adopted in the wake of the 2011 accident at the Fukushima No. 1 nuclear power plant — which set the operating period at “40 years in principle, extendable to a maximum of 60 years” will be changed, allowing plants to operate for “over 60 years.”
The NRA will compile a draft to amend the Law on the Regulation of Nuclear Source Material, Nuclear Fuel Material and Reactors, which sets the current rules, aiming to have it submitted at an ordinary Diet session next year. At its regular meeting Wednesday, the agency decided that it would discuss whether to formally accept the plan once the Economy, Trade and Industry Ministry has decided on its policy.
Under the current rules, when a nuclear plant reaches 40 years after the start of its operation, the NRA checks the “hard” aspects of the plant, meaning the safety of key physical facilities such as reactor buildings, and then grants a one-time extension of up to 20 years.
In addition, the watchdog has been taking measures to combat aging every 10 years for nuclear power plants that have been in operation for more than 30 years, by evaluating mainly the “soft” side, such as deterioration of parts, frequency of their replacement and adequacy of maintenance plans.
The NRA’s proposal seeks to unify the screening of the hard and soft sides. After 30 years of operation, nuclear plants will undergo safety inspections in terms of both sides before getting the green light for extended operation. After that, the NRA will check the status of deterioration for each plant, and give approval at intervals of within 10 years. The timing to first get approval for an extension thereby moves forward by 10 years from the current 40 years, and utilities would become able to operate nuclear power plants as long as they receive approval.
In regard to total operational life, the economy ministry is in discussions to decide to either eliminate upper limit, or to set a certain cap but not include periods when a plant is shut down. It will decide on a policy by the end of the year.
"Business" POPULAR ARTICLE
-
Japan Household Spending Down 0.5% in Feb.
-
Japan, U.S., Philippines to Strengthen Nickel Supply Chains; Reduce Reliance on China for Critical Minerals
-
Shinkansen to Have Private Rooms by FY 2026, JR Tokai Announces
-
Survey: 80% Worried About Recognizing AI as Patent Inventor; Respondents Fear Increase in Unverified Inventions
-
Ride-Sharing Services Start in Tokyo; Kanagawa, Aichi, Kyoto, Others To Follow Suit
JN ACCESS RANKING
- Japan Household Spending Down 0.5% in Feb.
- China Mutes Memorialization of Reformer Hu Yaobang; Memories Could Spark Critique of Xi Administration
- Shinkansen Services Suspended After Man ‘Searches for Phone’ on Tracks; Disruption Affects About 14,000 Passengers
- U.S. 7th Fleet officer Arrested on Suspicion of Stealing Sushi, Sashimi, Chicken at Kanagawa Shopping Mall; Suspect Caught Mid-Meal
- UNRWA Director Describes Catastrophic Destruction in Gaza; Says Relief Trucks Robbed, ‘People’s Hearts Destroyed’