Work proceeds on building tunnel to discharge treated water at Fukushima N-plant
12:55 JST, September 7, 2022
FUKUSHIMA — Tokyo Electric Power Company Holdings, Inc. held a press viewing of the construction site of an underwater tunnel leading to the ocean for discharging treated water from the Fukushima No. 1 nuclear power plant in Fukushima Prefecture.
The treated water is to be piped to an offshore discharge site through the tunnel, which is about 1-kilometer long.
On the seaward side of reactor Nos. 5 and 6, there is a shaft about 18 meters deep that leads to a tunnel with a diameter of 3.1 meters that extends toward the sea.
The walls of the tunnel are covered with reinforced concrete to prevent leakage.
A shield machine with many pipes and cables has been used to dig about 80 meters since Aug. 4.
A worker was monitoring the excavation amid the loud sound of the motor.
“Once the tunnel is excavated to 150 meters, the pace of excavation will be several times faster from that point forward,” said a TEPCO official. “We’ll proceed with safety as our top priority.”
The excavation is proceeding smoothly, but rough seas have prevented the installation of the discharge port at the end of the tunnel, which was scheduled to be done in August.
The ocean is expected to be even rougher in the winter. The failure to install the outlet before then could delay the construction work and possibly push back the start of water discharge, which is scheduled in the spring, to around summer.
"Society" POPULAR ARTICLE
-
M6.0 Earthquake Hits Japan’s Tohoku Region; Fukushima, Iwate, Miyagi Prefectures Observe 4 on Japanese Scale With No Risk of Tsunami
-
Shinkansen Services Suspended After Man ‘Searches for Phone’ on Tracks; Disruption Affects About 14,000 Passengers
-
U.S. 7th Fleet officer Arrested on Suspicion of Stealing Sushi, Sashimi, Chicken at Kanagawa Shopping Mall; Suspect Caught Mid-Meal
-
Tsunami Advisory for Okinawa Lifted at Noon (UPDATE 2)
-
JAL Airplane Experiences Radio Malfunction During Flight, Lands Safely By Relying on Light Signals
JN ACCESS RANKING
- M6.0 Earthquake Hits Japan’s Tohoku Region; Fukushima, Iwate, Miyagi Prefectures Observe 4 on Japanese Scale With No Risk of Tsunami
- China Mutes Memorialization of Reformer Hu Yaobang; Memories Could Spark Critique of Xi Administration
- Shinkansen Services Suspended After Man ‘Searches for Phone’ on Tracks; Disruption Affects About 14,000 Passengers
- U.S. 7th Fleet officer Arrested on Suspicion of Stealing Sushi, Sashimi, Chicken at Kanagawa Shopping Mall; Suspect Caught Mid-Meal
- UNRWA Director Describes Catastrophic Destruction in Gaza; Says Relief Trucks Robbed, ‘People’s Hearts Destroyed’