A construction worker on Tuesday handles a machine that is being used to build a tunnel at Fukushima No. 1 nuclear power plant to discharge treated water into the ocean.
12:55 JST, September 7, 2022
FUKUSHIMA — Tokyo Electric Power Company Holdings, Inc. held a press viewing of the construction site of an underwater tunnel leading to the ocean for discharging treated water from the Fukushima No. 1 nuclear power plant in Fukushima Prefecture.
The treated water is to be piped to an offshore discharge site through the tunnel, which is about 1-kilometer long.
On the seaward side of reactor Nos. 5 and 6, there is a shaft about 18 meters deep that leads to a tunnel with a diameter of 3.1 meters that extends toward the sea.
The walls of the tunnel are covered with reinforced concrete to prevent leakage.
A shield machine with many pipes and cables has been used to dig about 80 meters since Aug. 4.
A worker was monitoring the excavation amid the loud sound of the motor.
“Once the tunnel is excavated to 150 meters, the pace of excavation will be several times faster from that point forward,” said a TEPCO official. “We’ll proceed with safety as our top priority.”
The excavation is proceeding smoothly, but rough seas have prevented the installation of the discharge port at the end of the tunnel, which was scheduled to be done in August.
The ocean is expected to be even rougher in the winter. The failure to install the outlet before then could delay the construction work and possibly push back the start of water discharge, which is scheduled in the spring, to around summer.
"Society" POPULAR ARTICLE
-
Tokyo’s Off Limit Areas Becoming Popular for Tours
-
Tokyo’s Shibuya, Shinjuku Wards Take Measures to Prevent Disruptive Behavior and Brace for Foreign Tourist Surge on Halloween
-
Hokkaido Mountain Pass Covered in Snow as Many Areas of North Japan See First Snow of Year
-
Bear Spotted near Kyoto’s Arashiyama, Close to World Heritage Site Temple
-
Tatsuya Nakadai, Japanese Actor, Dies at 92; Appeared in Films Including “The Human Condition” and “Ran” (UPDATE 1)
JN ACCESS RANKING
-
Japan Logs Trade Deficit of 1,223 B. Yen in Fiscal 1st Half
-
Financial Services Agency Mulls Allowing Banks to Hold Cryptocurrencies; Will Also Discuss Establishing Risk Management Frameworks
-
Tokyo’s Off Limit Areas Becoming Popular for Tours
-
JR East Suica’s Penguin to Retire at End of FY2026; Baton to be Passed to New Character
-
South Korea to Hold Its Own Sado Island Gold Mines Memorial Service in November