Onagawa N-Plant’s Safety Measures Show Lessons Learned From 2011 Meltdown; Back-Up Power Source Kept High and Dry
The seawall built to protect Tohoku Electric Power Co.’s Onagawa nuclear power plant’s No. 2 reactor
20:00 JST, October 30, 2024
To protect Tohoku Electric Power Co.’s Onagawa nuclear power plant’s No. 2 reactor, safety measures have been put in place based on the new regulatory standards created after the 2011 meltdown of Tokyo Electric Power Company Holdings, Inc.’s disaster-hit Fukushima No. 1 nuclear power plant.
An 800-meter-long seawall, reaching 29 meters above sea level, has been built at the Onagawa plant. In addition, a gas turbine generator has been installed 60 meters above sea level to ensure a power supply even in the case of an accident. In the reactor building, a device has been installed to prevent hydrogen explosions by recombining any hydrogen that leaks from the containment vessel with oxygen.
Akio Yamamoto, a professor of nuclear engineering at Nagoya University, said, “[The standards are] more stringent than those of other countries, based on the idea of ‘taking all possible measures for safety,’ and took domestic and international disasters and research into consideration.”
The No. 2 reactor at Onagawa is a boiling water reactor, the same type that was used at the Fukushima No. 1 plant.
About 50 minutes after the 2011 Great East Japan Earthquake, a massive tsunami approximately 13 meters high – more than twice the maximum height assumed at the time – hit TEPCO’s Fukushima No. 1 plant, flooding almost the entire site. The power supply facilities, including emergency generators, were rendered inoperable, and critical functions such as reactor cooling and water circulation were lost, leading to a core meltdown.
Top Articles in Society
-
JAL, ANA Cancel Flights During 3-day Holiday Weekend due to Blizzard
-
Record-Breaking Snow Cripples Public Transport in Hokkaido; 7,000 People Stay Overnight at New Chitose Airport
-
Australian Woman Dies After Mishap on Ski Lift in Nagano Prefecture
-
Foreign Snowboarder in Serious Condition After Hanging in Midair from Chairlift in Nagano Prefecture
-
Train Services in Tokyo Resume Following Power Outage That Suspended Yamanote, Keihin-Tohoku Lines (Update 4)
JN ACCESS RANKING
-
Univ. in Japan, Tokyo-Based Startup to Develop Satellite for Disaster Prevention Measures, Bears
-
JAL, ANA Cancel Flights During 3-day Holiday Weekend due to Blizzard
-
China Confirmed to Be Operating Drilling Vessel Near Japan-China Median Line
-
China Eyes Rare Earth Foothold in Malaysia to Maintain Dominance, Counter Japan, U.S.
-
Japan Institute to Use Domestic Commercial Optical Lattice Clock to Set Japan Standard Time